← Back to Blog

LADs Explained — What They Are, How They Work, and How to Challenge Them

Liquidated and Ascertained Damages — universally known as LADs — are one of the most feared clauses in any construction subcontract. And for good reason. An unfair LAD clause, poorly understood, can turn a profitable job into a significant loss.

But LADs are also one of the most misunderstood clauses in construction contracts. Many subcontractors accept them without question, not realising that they have more room to negotiate and challenge than they think.

What are LADs?

Liquidated and Ascertained Damages are a pre-agreed rate of compensation that the main contractor can deduct from your payments if you fail to complete your works by the completion date. They're 'liquidated' because the amount is fixed in advance — rather than the main contractor having to prove their actual loss.

The theory behind LADs is sensible. Rather than going to court to prove the exact financial impact of a delay, the parties agree a reasonable rate in advance. It gives both sides certainty. The problem is when the rate isn't reasonable — when it's a penalty rather than a genuine estimate of loss.

How LADs Work Under a JCT Subcontract

The Extension of Time Mechanism — Your Protection

The most important protection against unfair LADs is the extension of time mechanism. Under a JCT subcontract, you are entitled to an extension of time if delay is caused by certain events — called 'relevant events' — that are outside your control.

Standard relevant events include:

⚠️ Watch Out

The relevant events clause is one of the most commonly amended clauses in subcontracts. Main contractors sometimes narrow the list, making it harder for you to claim an extension of time. Always check this clause — if relevant events don't include delays caused by the main contractor themselves, that's a significant problem.

Can You Challenge a LAD Rate?

Yes — and this surprises many subcontractors. LADs must be a genuine pre-estimate of the main contractor's loss caused by your delay. They cannot be a penalty. If the rate is so high that it couldn't reasonably represent the actual loss, it may be legally unenforceable.

The law in this area was clarified by the Supreme Court in Cavendish Square v Makdessi (2015), which established that a clause is a penalty — and therefore unenforceable — if it imposes a detriment out of all proportion to any legitimate interest of the innocent party.

💡 Kontrak Tip

Before you sign, ask the main contractor how the LAD rate was calculated. A reasonable LAD rate should relate to the actual cost of delay — prolongation costs, additional management time, potential claims from the employer. If they can't explain the calculation, that's worth probing.

How to Protect Yourself Against Unfair LADs

Before You Sign

During the Contract

If LADs Are Applied

A Real-World Example

Consider a subcontractor on a £250,000 commercial fit-out contract with LADs of £2,500 per week and a 10% cap. Their maximum LAD exposure is £25,000.

Midway through the project, the main contractor's structural works overrun by three weeks, preventing the subcontractor from accessing their work area. The subcontractor finishes three weeks late as a result.

Without an extension of time, the main contractor attempts to deduct £7,500 in LADs. But because the delay was caused by the main contractor's own programme overrun — a relevant event — the subcontractor is entitled to a three-week extension. The LAD deduction falls away entirely.

The key was that the subcontractor had kept a programme, documented the access restriction, and issued an extension of time notice at the time the delay occurred. Without that documentation, the claim would have been much harder to pursue.

Review your JCT subcontract before you sign — in minutes, not days.

Join the Waiting List at kontrak.co.uk →
This article is provided for information purposes only and does not constitute legal advice. Always consult a qualified solicitor for advice on your specific circumstances.
Next: Pay-Less Notices →